Where the Hamilton light rail line will run, who is building it, what is known about the timeline, the LRT work zones now posted, and where to get construction updates.

Every answer sourcedAdministered by Metrolinx, the provincial transit agency, owns the Hamilton LRT and is responsible for delivering it; the City of Hamilton's LRT Project Office works with Metrolinx and delivers some enabling works. Every answer below was checked against its source on November 26, 2026; the source is linked under each one.

The short answer

The Hamilton LRT is a 14-kilometre, 17-stop light rail line on its own tracks from McMaster University to Eastgate Square, along Main Street, King Street and Queenston Road. Metrolinx picked Hamilton Transit Alliance, led by Aecon Infrastructure, for the first civil and utility work in spring 2026 and says timelines will be set in an 18-to-24-month development phase; no opening date had been published when this page was checked on November 26, 2026.

Last verified

From 9 official sources, administered by Metrolinx, the provincial transit agency, owns the Hamilton LRT and is responsible for delivering it; the City of Hamilton's LRT Project Office works with Metrolinx and delivers some enabling works.

Route and stops

2 questions
  1. Where will the Hamilton LRT run?

    From McMaster University in the west to Eastgate Square in the east, a 14-kilometre line on its own dedicated tracks, separate from regular traffic, along Main Street, King Street and Queenston Road through downtown Hamilton. Metrolinx says it will have 17 stops, including stops at McMaster University, Hamilton Stadium, Ottawa Street, Gage Park, downtown Hamilton and Eastgate Square, with connections to GO Transit and HSR buses. It expects about 50,000 riders a day and 16,400 new daily transit trips.

    Length
    14 km, McMaster University to Eastgate Square
    Stops
    17
    Expected ridership
    About 50,000 riders a day

    Watch for: Metrolinx's spring 2025 conceptual design shows the route in detail, but Metrolinx calls it a snapshot in time that is subject to change as the design is refined.

    Source: Metrolinx, Major Hamilton LRT contract awarded

  2. Will the LRT use HSR fares?

    Yes. The City of Hamilton says LRT fares will be set by the City and will integrate with existing HSR service as one system, for seamless transfers. The City also says the trains will have level boarding with no steps or ramps, and that bikes will be allowed on the vehicles during off-peak service.

    Watch for: The City has not posted LRT fare amounts; current HSR fares are on this site's fares guide.

    Source: City of Hamilton, Light Rail Transit (LRT)

Who is building and running it

3 questions
  1. Who is building the Hamilton LRT?

    Metrolinx owns the project. It selected Hamilton Transit Alliance, led by Aecon Infrastructure with Hatch, Egis and Systra as designers, to deliver the first major package of work: preparatory work along the route, including utility relocations, grade separations, road reconstruction and upgraded sidewalks and traffic control systems. Under this alliance model, Metrolinx partners directly with the private companies rather than administering a third-party consortium. A second procurement will cover the stops, rail and LRT systems.

    Watch for: Metrolinx had not named a builder for the second package (stops, rail and systems) when this page was checked on November 26, 2026.

    Source: Metrolinx, Major Hamilton LRT contract awarded

  2. What does the first LRT contract include, and who is paying for it?

    The Province announced on April 30, 2026 that Hamilton Transit Alliance, led by Aecon Infrastructure Inc., had been awarded the Hamilton LRT Civil and Utilities contract. The Province says the contract will also advance design work to replace the bridge over Highway 403, build a new LRT underpass beneath the CPKC rail line near Gage Avenue and improve the Queenston Road bridge over the Red Hill Valley Parkway. The provincial and federal governments are investing up to $3.4 billion in the Hamilton LRT.

    Sewer replacement and separation
    14 km
    Watermain replacement
    16 km
    Road reconstruction
    14 km
    Sidewalks replaced and upgraded
    28 km
    Traffic signals upgraded or replaced
    62

    Watch for: The Province says the work will create approximately 6,000 jobs a year during construction and up to 1,000 permanent jobs in operations and maintenance.

    Source: Government of Ontario, Ontario Begins Civil and Utility Work for Hamilton LRT

  3. Who will operate the Hamilton LRT?

    That had not been decided when this page was checked on November 26, 2026. Metrolinx says it has received the City of Hamilton's operations and maintenance proposal and is reviewing it, and that it will work with the City to make sure operations are delivered in the way that best serves customers and residents.

    Source: Metrolinx, Hamilton LRT: FAQs

Timeline

2 questions
  1. When will the Hamilton LRT open?

    No opening or completion date had been published when this page was checked on November 26, 2026. Metrolinx says that with the first contract awarded, the project entered an alliance development phase, lasting 18 to 24 months, to progress the design, costs and construction schedule, and that construction timelines and final costs will be finalized during that phase together with Hamilton Transit Alliance.

    Watch for: The City told Council on April 30, 2026 that major construction follows the development phase. A schedule, when there is one, will appear on Metrolinx's Hamilton LRT pages.

    Source: Metrolinx, Hamilton LRT: FAQs

  2. What LRT work has already been done?

    The City calls the current stage enabling works, or early works: underground projects completed before major construction to prepare the way for it. Metrolinx funds them, and some are delivered through City of Hamilton contracts coordinated with planned City infrastructure work. The City's 2026 enabling projects are lowering a 1200 mm trunk watermain on Nash Road under the future guideway at Queenston Road, moving a 1200 mm trunk watermain from Queenston Road to a new alignment on Rosewood Road and Main Street East, and several trunk watermains on Main Street East from Grosvenor Avenue to London Street, at Ottawa Street.

    Watch for: Already completed: a 300 mm watermain on Sherman Avenue from Cumberland Avenue to Wilson Street and a 500 mm trunk watermain on Wentworth Street from King Street to Wilson Street. Metrolinx's FAQs add that utility relocations, property acquisitions, demolitions and archaeological work have been done and will continue.

    Source: City of Hamilton, LRT Enabling Works

Current work zones and closures

3 questions

As each source posted them on the day this page was checked. Short closures change week to week; the City's list is the up-to-date record.

  1. When does the Main Street East and Ottawa Street intersection reopen?

    The City scheduled the intersection of Main Street East and Ottawa Street North to reopen to two-way traffic on Thursday, December 17, 2026. It has been fully closed since Monday, August 17, 2026 for early utility work for the LRT, replacing City watermains and sewers and Bell Canada infrastructure. Some construction may continue nearby after the reopening. During the closure, westbound Main Street traffic is detoured north on Kenilworth Avenue and west on Cannon Street, and eastbound traffic uses King Street at the Delta.

    Watch for: HSR routes 1 and 1A King, 10 B-Line and 41 Mohawk are on detour with stops out of service; check the City's page and HSR detours before you travel.

    Source: City of Hamilton, Main & Ottawa Closure Updates

  2. Which other streets have LRT lane closures?

    On November 26, 2026, the City's list of lane restrictions and road closures showed these for LRT work: King Street East from Belmont Avenue to Hughson Street North, from Monday, October 26 to Friday, December 11; Queenston Road from Rosewood Road to Centennial Parkway, including the Queenston Traffic Circle, from Monday, November 9 to January 25, 2027; King Street West from Hughson Street North to New Street, November 23 to December 18; and lane occupancies at Cootes Drive and Leland Street at Main Street East on Saturday, November 28 from 6 p.m. to 10 p.m.

    Watch for: The list does not say how many lanes are occupied. It also lists lane restrictions on Nash Road at King Street and Queenston Road for water works, August 31 to the end of December 2026.

    Source: City of Hamilton, Lane Restrictions and Road Closures

  3. What is the Metrolinx utility inspection work along the LRT route?

    Metrolinx is carrying out corridor-wide utility investigations along the future LRT route from August 31 to December 31, 2026, Monday to Sunday, 7 a.m. to 7 p.m., to confirm the location and condition of underground utilities for the detailed design. Metrolinx says to expect minor delays near work zones, with two-way traffic maintained and a paid duty officer, flaggers and detour signs where needed. Businesses stay open, and pedestrian detours may be signed.

    Watch for: Metrolinx says some HSR bus stops will be closed for periods during the work, with signs posted, and that work may be delayed or rescheduled because of weather.

    Source: Metrolinx, Hamilton LRT Corridor-Wide Utility Investigations

Updates and questions

1 question
  1. Where do I get Hamilton LRT construction updates or ask a question?

    Metrolinx's Hamilton LRT community engagement team takes questions at 905-521-1003 or hamilton@metrolinx.com, and through a form on its contact page. Its community office at 116 King Street East in Hamilton is open Tuesdays and Thursdays from 10 a.m. to 3 p.m. and at other times by appointment. Metrolinx posts construction notices on its Hamilton LRT notices page and offers email updates you can sign up for on its project page.

    Watch for: For City-delivered work and closures, the City's LRT Project Office is at lrtprojectoffice@hamilton.ca, and current closures are on the City's lane restrictions list.

    Source: Metrolinx, Hamilton LRT: Contact Us

Official sources and contacts

9 official pages
MetrolinxMajor Hamilton LRT contract awardedThe official page this guide’s first answer is checked against. The office that runs the service has the final word on a case of your own.Open metrolinx.com
Who to contact
Metrolinx Hamilton LRT community engagement team
905-521-1003, hamilton@metrolinx.com
City of Hamilton LRT Project Office
lrtprojectoffice@hamilton.ca

Sources

  1. MetrolinxMajor Hamilton LRT contract awardedPublished May 4, 2026 · Retrieved November 26, 2026
  2. City of HamiltonLight Rail Transit (LRT)Published November 13, 2026 · Retrieved November 26, 2026
  3. Government of OntarioOntario Begins Civil and Utility Work for Hamilton LRTPublished April 30, 2026 · Retrieved November 26, 2026
  4. MetrolinxHamilton LRT: FAQsRetrieved November 26, 2026
  5. City of HamiltonLRT Enabling WorksPublished November 17, 2026 · Retrieved November 26, 2026
  6. City of HamiltonMain & Ottawa Closure UpdatesPublished November 18, 2026 · Retrieved November 26, 2026
  7. City of HamiltonLane Restrictions and Road ClosuresPublished November 26, 2026 · Retrieved November 26, 2026
  8. MetrolinxHamilton LRT Corridor-Wide Utility InvestigationsPublished August 28, 2026 · Retrieved November 26, 2026
  9. MetrolinxHamilton LRT: Contact UsRetrieved November 26, 2026

Every answer on this page traces to one of these documents.

Last checked 9 official pages from Metrolinx, City of Hamilton, Government of Ontario

Recent reporting

HamiltonIQ stories on this topic, each with its own sources and date.