When will the Hamilton LRT be finished? No completion date has been published

The 14-km, 17-stop Hamilton LRT entered an 18-to-24-month development phase after the Province picked a builder on April 30, 2026. Metrolinx says construction timelines and final costs will be set during that phase; no opening date is published.

HamiltonIQ Newsroom7 sources · 3 min read

Email

The details

The short answer

No completion date has been published. As of October 11, 2026, Metrolinx, which owns and is delivering the project, says the project has entered an alliance development phase to progress designs, costs and the construction schedule, that the phase will last 18 to 24 months, and that construction timelines and final costs will be finalized during it. The Province's April 30, 2026 announcement and the City of Hamilton's LRT page also give no construction start, completion or opening date.

Hamilton LRT: confirmed and not confirmed (checked October 11, 2026)
Length
14km, McMaster University to Eastgate Square
Stops
17
Expected ridership
About 50,000 riders a day; 16,400 new daily transit trips
First contract (civil and utilities)
Awarded April 30, 2026 to Hamilton Transit Alliance, led by Aecon Infrastructure
Development phase
18 to 24 months, from the contract award
Second contract (stops, rail and systems)
A separate procurement; no date published
Funding
Up to $3.4 billion from the Province and the federal government
Start of major construction
Not published
Completion or opening date
Not published

The April 30 contract

On April 30, 2026, the Province announced that Hamilton Transit Alliance, led by Aecon Infrastructure Inc., had been awarded the Hamilton LRT Civil and Utilities contract, the first major package of work. Metrolinx says Hatch, Egis and Systra are the alliance's designers. The contract covers preparatory work along the route, including utility relocations, grade separations, road reconstruction and upgraded sidewalks and traffic control systems. The Province says it will also advance design work to replace the bridge over Highway 403, build a new LRT underpass beneath the CPKC rail line near Gage Avenue and improve the Queenston Road bridge over the Red Hill Valley Parkway.

In an alliance, Metrolinx partners directly with the private companies rather than administering a third-party consortium. The City's Communication Update to Council the same day said the alliance partner will work with the Province over 18 to 24 months during the Development Phase to advance the design and construction planning of the first package, followed by major construction, including developing construction schedules and finalizing a target price. Metrolinx says a second procurement will cover the stops, rail and LRT systems.

City infrastructure the first contract will replace, according to the Province and Metrolinx
Sewer replacement and separation
14km
Watermain replacement
16km
Road reconstruction
14km
Sidewalks replaced and upgraded
28km
Traffic signals upgraded or replaced
62

Route and stops

The line will run on its own dedicated tracks, separate from regular traffic, from McMaster University in the west to Eastgate Square in the east, according to the City. Metrolinx describes a 14-kilometre corridor with 17 stops along Main Street, King Street and Queenston Road, with connections to GO Transit and HSR buses. The Province and Metrolinx name stops at McMaster University, Hamilton Stadium, Eastgate Square, Ottawa Street, Gage Park and downtown Hamilton, among other destinations.

Metrolinx's conceptual design booklet from spring 2025, which it says is a snapshot in time that is subject to change, routes the line along Main Street West, Dundurn Street, King Street, Main Street East and Queenston Road, ending at Centennial Parkway, and includes renderings of stops at Queen Street, Wellington Street and Parkdale Avenue. The City says LRT fares will be set by the City and integrated with HSR service.

What is already under way

Metrolinx says utility relocations, property acquisitions, demolitions and archaeological work have been completed as advance enabling works and will continue during the development phase. The City's own pre-LRT work includes the full closure of the Main Street East and Ottawa Street North intersection, which began on August 17, 2026.

  • Metrolinx project questions: Hamilton@metrolinx.com or 905-521-1003.
  • City LRT page, with Council reports and closure updates: hamilton.ca, Light Rail Transit (LRT).
  • This page will be updated when a construction schedule is published.

Sources

Every factual claim above traces to one of these documents.

  1. Province of Ontario

    Ontario Begins Civil and Utility Work for Hamilton LRT

    Published April 30, 2026 · Retrieved October 11, 2026

  2. City of Hamilton

    Communication Update: Hamilton LRT Procurement Update – Selection of Alliance Partner for Package 1

    Published April 30, 2026 · Retrieved October 11, 2026

  3. City of Hamilton

    Light Rail Transit (LRT)

    Published September 16, 2026 · Retrieved October 11, 2026

  4. Metrolinx

    Hamilton LRT: FAQs

    Retrieved October 11, 2026

  5. Metrolinx

    Major Hamilton LRT contract awarded

    Retrieved October 11, 2026

  6. Metrolinx

    Hamilton LRT: What We're Building

    Retrieved October 11, 2026

  7. Metrolinx

    Hamilton LRT Conceptual Design (Spring 2025)

    Retrieved October 11, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.