Hamilton building permits: apply, fees, inspections

How the permit process works from application to final inspection, what it costs and what delays it.

Summary

A Hamilton building permit is applied for and paid online through the City's Customer Portal at my.hamilton.ca, and is issued only if the project meets the Ontario Building Code, the Zoning By-law and other applicable law. Fees follow Building By-law No. 15-058, with a minimum of $291, and are higher if work started without a permit. Inspections at set stages are mandatory and are booked at 905-546-2424 ext. 7777.

Administered by the City of Hamilton's Building Division. Every answer below was checked against its source on November 18, 2026; the source is linked under each one.


Before you apply

What is a building permit, and what is it checked against?

A building permit legally authorizes you to start construction in accordance with approved drawings and specifications. The City reviews an application for compliance with the Ontario Building Code, Hamilton's Zoning By-law, Niagara Escarpment Commission and conservation authority regulations, and other applicable provincial and municipal regulations. Its purpose is to make sure zoning requirements and fire, structural and other building standards are met.

Source: City of Hamilton, Building Permit Application Requirements

What if my project does not meet the Zoning By-law?

A permit is issued only if the project complies with the Zoning By-law for the property, which governs size, setbacks, location, height and parking. Check the zone on the City's interactive zoning map, or contact the Planning Division at 905-546-2424 ext. 2719 while you are still planning. If the project cannot comply, you can apply to the Committee of Adjustment for a minor variance, and then apply for the permit on the terms the committee sets.

Source: City of Hamilton, Building Permit Application Requirements

What other approvals can hold up a building permit?

Approvals under applicable law, which must be in hand before a permit can be issued. The City's examples include a Heritage Permit, a permit from the conservation authority for the watershed, a Development Permit from the Niagara Escarpment Commission, and, near the LRT corridor, a Corridor Development Permit from Metrolinx. A completed Applicable Law Checklist is required with certain applications.

The four conservation authorities with land in Hamilton are the Hamilton, Halton, Grand River and Niagara Peninsula authorities; a Natural Heritage Planner at 905-546-2424 ext. 1355 can say what features affect a property.

Source: City of Hamilton, Building Permit Application Requirements

Can I draw my own plans, or do I need a designer?

As the owner you may design your own project and prepare your own drawings. Most designs that are not done by the owner must be prepared by a designer who is registered or qualified under the Ontario Building Code and holds a Building Code Identification Number (BCIN). Some projects, including most industrial, commercial and institutional construction, need drawings stamped by an architect, a professional engineer or both.

The City suggests getting three or more quotes before hiring a designer, and checking with the Building Division at 905-546-2720 whether your project needs a qualified one.

Source: City of Hamilton, Hiring a Designer for Building Permit Drawings

When is a professional grading plan required?

For residential infill (single family, two family and semi-detached houses), residential additions, residential accessory buildings and detached additional dwelling units, unless an exemption applies. The plan must be prepared, sealed and signed by an Ontario land surveyor, professional engineer, architect or landscape architect, who also reviews the work and certifies the as-built grading; a grading security deposit is due with the application.

Exempt, where no drainage features or property-line grades change: an addition or accessory building of no more than 55 square metres that is at least 1.0 m from property lines, or a larger one at least 3.0 m away, and projects on lots of at least 0.4 hectares kept 3.0 m from property lines.

Source: City of Hamilton, Building Permit Application Requirements


Applying and review

How do I apply for a building permit in Hamilton?

Online, through the City's Customer Portal. Visit my.hamilton.ca, select Login/Register to create an account, then go to Getting Started and choose Permitting & Inspections. The owner, or an agent acting for the owner, can apply. Documents must be PDFs that are not password protected, plans must be vector-based PDFs drawn to scale, and drawings are submitted in black and white with clear file names.

For a house or other one- or two-unit residential project, all drawings can be combined in a single PDF; larger projects submit one PDF per discipline.

Source: City of Hamilton, Building Permit Application Requirements

What happens after I submit the application?

Staff review it in stages: zoning and applicable law, Building Code plan review, mechanical plans examination where heating, plumbing or septic work is involved, and fire prevention examination for some larger buildings. If more information is needed, you receive a list of items to address before the permit can be approved. If the project complies, the permit is issued; if not, you are issued a notice documenting why.

An application that stays incomplete or inactive for six months may be deemed abandoned, and cancelled if the applicant does not respond within 10 business days of written notice.

Source: City of Hamilton, Building Permit Review and Approval

Does my contractor need a City licence?

Yes. Building repair contractors (such as roofers, carpenters, bricklayers, window and door installers and waterproofing contractors), drain, plumbing, heating and air conditioning, and fire sprinkler contractors must hold a valid City of Hamilton trade licence, and you must give the licence number of the contractor doing the work when you apply for the permit. The City publishes a searchable list of licensed contractors.

It is the owner's responsibility to get a building permit, if one is needed, before construction starts.

Source: City of Hamilton, Building Permit Application Requirements


Fees and refunds

How are building permit fees calculated?

Most fees are a service index, in dollars per square metre for the class of work, multiplied by the floor area involved, rounded to the nearest dollar, with a minimum permit fee of $291. Where no new floor area is created, the fee is 1 per cent of the prescribed value of the work, subject to the minimum. Fees are paid online in full when you apply; where a fee exceeds $50,000, an applicant may pay 55 per cent on application and the balance at issuance.

Minimum permit fee
$291
Detached, semi-detached or row house
$18.32 per m²
Apartment buildings
$18.32 per m²
Alterations to existing finished areas
$4.06 per m²
Demolition of a house
$0.54 per m²
Residential foundation permit
$453 flat fee

A proposed 3 per cent increase to building permit fees goes to a public meeting of the Planning Committee on December 1, 2026. Development charges and parkland dedication fees may also apply.

Source: City of Hamilton, Building Permit Fees

What does it cost if work started without a permit?

An additional fee on top of the regular permit fee, set by Schedule C of the Building By-law as a percentage increase: 25 per cent if footings, foundations or other work needing a permit has started, 50 per cent if structural framing has started, 75 per cent if framing is complete, and 100 per cent if the work, or a demolition, is complete.

Building without a permit can also bring an order to comply registered on title, a stop work order and prosecution; the City cites maximum fines under the Building Code Act of $50,000 for an individual and $500,000 for a corporation for a first offence.

Source: City of Hamilton, By-law No. 15-058, Building By-law (Office Consolidation)

Can I get a refund if I withdraw my application?

On written request, yes, as a percentage of the fee that depends on how far the City got: 80 per cent if only administrative functions were performed, 70 per cent after zoning review, 45 per cent after plan examination, and 35 per cent once the permit is issued, less 5 per cent for each field inspection performed. No refund is made of an amount less than the minimum permit fee.

The by-law allows no refund where a permit has been revoked under paragraphs 8(10)(a) or (f) of the Building Code Act.

Source: City of Hamilton, By-law No. 15-058, Building By-law (Office Consolidation)

What other building permit charges should I expect?

The fee schedule lists $187 for a revision after the permit is issued, $187 an hour for reviewing a second or later non-compliant resubmission, $187 to extend or transfer a permit, $248 for an inspection that was requested too early and has to be repeated, and $285 for an applicable law review. A conditional permit costs 10 per cent of the permit fee, with a minimum of $1,219 and a maximum of $4,267.

Source: City of Hamilton, Building Permit Fees


Inspections and occupancy

How do I book a building inspection?

Call 905-546-2424 ext. 7777 on weekdays from 8:30 a.m. to 4:30 p.m., email building@hamilton.ca, or, for permits applied for through the Customer Portal, book through my.hamilton.ca. Have the permit number, address, preferred date and time, and type of inspection ready. Inspection requests are completed within 2 business days. The permit must be posted on site and the approved drawings available for every inspection.

If the work is not ready and you do not cancel before the inspector arrives, you may be charged an additional fee.

Source: City of Hamilton, Building Inspections

Which inspections are required?

It depends on the work, but the City's stages include a pre-construction site meeting, footings before the pour, backfill, sewer and water services, building drains, radon and underslab insulation before the floor slab, plumbing and HVAC rough-in, structural framing before any insulation, air barrier, insulation and vapour barrier before drywall, fire separations, fire protection systems, occupancy, grading and a final inspection.

The inspections are mandatory under the Ontario Building Code; missing one may mean uncovering completed work.

Source: City of Hamilton, Building Inspections

When can I move into a new or renovated building?

After an occupancy inspection, requested on substantial completion and before the building is occupied. The inspector checks that interior components such as life safety systems, finishes and washrooms are complete, along with minimum exterior items including cladding, grading around the building and the principal entrance. The request must come with the City's occupancy permit application form.

Where a grading plan was required, final grading and the consultant's certificate must be complete before the final inspection.

Source: City of Hamilton, Building Inspections

Sources

Every factual claim above traces to one of these documents.

  1. City of Hamilton

    Building Permit Application Requirements

    Retrieved November 18, 2026

  2. City of Hamilton

    Hiring a Designer for Building Permit Drawings

    Retrieved November 18, 2026

  3. City of Hamilton

    Building Permit Review and Approval

    Retrieved November 18, 2026

  4. City of Hamilton

    Building Permit Fees

    Retrieved November 18, 2026

  5. City of Hamilton

    By-law No. 15-058, Building By-law (Office Consolidation)

    Retrieved November 18, 2026

  6. City of Hamilton

    Building Inspections

    Retrieved November 18, 2026