Hamilton development charges: 2026-27 rates

What development charges are, the current rates by area and unit type, exemptions and when they are paid.

Summary

Development charges are one-time fees the City of Hamilton collects on new development, under By-law No. 24-072, to pay for the roads, transit, water, sewers and emergency services that growth requires. From June 1, 2026 to May 31, 2027 the full City rate for a single or semi-detached house ranges from $44,415 in the rural area to $102,451 in the separated sewer system Urban Area A, before exemptions. Ask for an estimate at 905-546-2424 ext. 4400.

Administered by the City of Hamilton, which also collects the school boards' education development charges. Every answer below was checked against its source on November 18, 2026; the source is linked under each one.


What development charges are

What are development charges?

One-time fees collected from developers to help pay for the infrastructure that growth requires, including roads, transit, water and sewer infrastructure, and fire and police services. The City says they exist so that the cost of new infrastructure is not passed on to existing property taxpayers through higher taxes and water bills. If a project requires a building permit, development charges may apply.

Source: City of Hamilton, Development Charges

Which development charges apply in Hamilton?

Three: City development charges under the Development Charges Act, 1997 and City of Hamilton By-law No. 24-072, and two education development charges, one under each school board's own by-law. The City is responsible for its charges and each board for its own, but the City collects all three. Some areas also pay a special area charge, mapped in the pamphlet for Waterdown and Dundas.

An amended By-law No. 24-072 with updated exemptions took effect on October 7, 2026.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

How are the rates set, and when do they change?

Council passes a development charges by-law after a background study that forecasts development and population, reviews past service levels and lists the capital projects growth will need. The by-law provides for annual adjustments, and the pamphlet states that rates increase on June 1 of each year. Hamilton's current background study and by-law date from 2024.

A 2025 fact sheet says the City was considering changes including letting Council stop automatic annual increases and extending the rate transition period from 6 to 12 months; check the current by-law for what was adopted.

Source: City of Hamilton, Development Charges


Current rates

Rates in effect from June 1, 2026 to May 31, 2027, before exemptions and credits.

How much are development charges on a new house in Hamilton?

From June 1, 2026 to May 31, 2027, the full City charge on a single or semi-detached house is $44,415 in the rural area, $89,729 in the combined sewer system Urban Area A, $102,451 in the separated sewer system Urban Area A and $53,410 in the separated sewer system Urban Area B. Education development charges add $3,579 per unit. The pamphlet's maps show which area a property is in.

Single or semi-detached, rural area
$44,415
Single or semi-detached, combined sewer Urban Area A
$89,729
Single or semi-detached, separated sewer Urban Area A
$102,451
Single or semi-detached, separated sewer Urban Area B
$53,410
Education development charges, per unit
$3,579
Special area charge, single or semi-detached
$1,931

These are full rates. Partial exemptions currently reduce the City portion, and the City will prepare an informational estimate on request at DCRequest@hamilton.ca.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

What are the rates for townhouses and apartments?

In the combined sewer system Urban Area A, the full City rate from June 1, 2026 to May 31, 2027 is $66,971 for a townhouse or other multiple unit, $55,006 for an apartment or stacked townhouse with two or more bedrooms, $34,087 for a one-bedroom or bachelor apartment, and $27,935 for a residential facility or lodging house unit. The pamphlet gives the matching rates for the rural area and for the separated sewer system areas.

Townhouse or other multiple, rural area
$33,150
Townhouse or other multiple, separated sewer Urban Area A
$76,468
Apartment, 2+ bedrooms, separated sewer Urban Area A
$62,806
Apartment, 1 bedroom or bachelor, separated sewer Urban Area A
$38,919
Apartment, 1 bedroom or bachelor, separated sewer Urban Area B
$20,290

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

What do businesses pay?

Non-residential rates are per square foot. From June 1, 2026 to May 31, 2027 the full City rate for non-industrial development is $21.08 in the rural area, $39.85 in the combined sewer system Urban Area A, $46.88 in the separated sewer system Urban Area A and $26.81 in Urban Area B. Industrial rates are lower, and lower again for manufacturing, production studios and artist studios. Education development charges are $1.57 per square foot from July 1, 2026.

Reductions include a 37 per cent partial exemption for manufacturing, production studio and artist studio development and full exemptions for places of worship, farm business development and non-profit child care centres.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

What does the money pay for?

The pamphlet breaks each rate down by service. Of the $44,415 charged on a single or semi-detached house everywhere in the city, $21,236 is for services related to a highway, $12,979 for parks and recreation, $2,418 for libraries, $1,878 for transit, $1,566 for public works, $1,350 for fire protection and $1,194 for police. Urban areas add charges for water, wastewater and stormwater services.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027


Exemptions and credits

What exemptions reduce residential development charges?

The pamphlet lists a 20 per cent partial exemption between September 1, 2025 and August 31, 2027; a 4 per cent partial exemption between June 1, 2026 and May 31, 2027; a 15 to 25 per cent exemption for rental housing based on the number of bedrooms in each unit; a 30 per cent partial exemption for residential development in the Downtown Hamilton Community Improvement Project Area, within set height limits; and full exemptions for non-profit housing and long-term care homes.

Exemptions apply to City development charges in accordance with the Act and the by-law; where the pamphlet and the by-law differ, the by-law governs.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

Do I get a credit if I demolish a building and rebuild?

Yes. A demolition credit reduces the development charges payable on a new development when a building has been demolished under a demolition permit. The credit is available for up to 5 years after the demolition permit is issued, applies to both City and education charges, and is valued at the rate in effect at the time of redevelopment. No credit is given if the demolished building is exempt under the current by-law.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027


Paying, locking in a rate and disputes

When are development charges paid?

Education development charges are payable before the building permit is issued. City charges depend on the type of development: non-rental residential development pays in one full payment at occupancy; rental housing and institutional developments pay in six yearly payments starting at occupancy; and non-residential, non-institutional development pays in full when the building permit is issued.

The City may allow delayed payment for some developments, and runs a deferral program for which a minimum development charge of $50,000 is required to apply.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

Which rate applies to my project?

Usually the rate in effect on the day the building permit is issued. Under the City's transition policy, if the permit is issued within 6 months of a rate increase, the rate in effect when the permit application was made applies. Where a site plan or zoning by-law amendment application was submitted on or after January 1, 2020, the rate can instead be locked in at the application date, provided the permit is issued within the time the Act requires after approval.

Neither the transition policy nor the rate lock-in applies to education development charges.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

Can I dispute a development charge?

Yes. Anyone required to pay a development charge may complain to City Council under section 20 of the Development Charges Act if they believe the amount was incorrectly determined, a credit was not applied or was miscalculated, or the by-law was applied in error. The complaint must be made in writing to the City Clerk, must state that it is a section 20 complaint, and must be submitted within 90 days of when the charge, or any part of it, is payable.

Documents submitted with a complaint become part of the public record.

Source: City of Hamilton, City of Hamilton Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027

What other growth charges are there besides development charges?

Two. A Community Benefits Charge under By-law No. 22-158 applies to development of five or more storeys with ten or more residential units, and is paid as a one-time fee of 4 per cent of the land value on the day before the building permit is issued. Parkland dedication under By-law No. 22-218 requires land for parks, or fees, as a condition of development, and is separate from development charges.

Source: City of Hamilton, Community Benefits Charges

Sources

Every factual claim above traces to one of these documents.

  1. City of Hamilton

    Development Charges

    Retrieved November 18, 2026

  2. City of Hamilton

    Community Benefits Charges

    Retrieved November 18, 2026