LRT work moves to Queenston Road and the Queenston Traffic Circle from November 9 to January 25
The City lists an LRT lane occupancy on Queenston Road, Rosewood Road to Centennial Parkway and the traffic circle, from Monday, November 9 to January 25, 2027. Green and Grays road rail crossings and a block of Bay Street also close next week.
The details
Queenston Road
The City of Hamilton's list of scheduled lane restrictions and road closures, last modified November 5, 2026, shows a lane occupancy on Queenston Road from Rosewood Road to Centennial Parkway, including the Queenston Traffic Circle, starting Monday, November 9 and ending January 25, 2027. The reason given is LRT work. The list does not say how many lanes will be occupied or at what hours.
The City says the LRT will run on its own tracks from McMaster University in the west to Eastgate Square in the east. This is the first LRT entry on the City's closures list for Queenston Road, east of the King Street East and Main Street East work already under way: King Street East from Belmont Avenue to Hughson Street North is listed to December 11, and Main Street East from Edgemont Street to Fairfield Avenue to November 11. King Street West from Hughson Street North to New Street follows from November 23 to December 18.
Separately, Nash Road at Queenston Road has a lane occupancy for road work from 7 a.m. Monday, November 9 to 7 a.m. Wednesday, November 11. The list does not tie that work to the LRT.
Other closures starting next week
- Closed 7 a.m. Monday, November 9 to 7 p.m. Friday, November 13 (CN Rail work)
- Closed 7 a.m. Monday, November 9 to 7 p.m. Friday, November 13 (CN Rail work)
- Closed 9 a.m. Tuesday, November 10 to 4 p.m. Tuesday, November 24 (crane works)
- Lane occupancy Saturday, November 7 to Sunday, November 8, then Monday, November 9 to Friday, December 11 (building demolition)
- Lane occupancy 7 a.m. to 5 p.m. daily from Tuesday, November 10 to 5 p.m. Thursday, November 12 (watermain work)
- Closed 7 a.m. Tuesday, November 10 to 7 p.m. Thursday, November 12 (road work)
The Kenilworth Access also has a lane occupancy west of the Mountain Brow Traffic Circle from 9 a.m. to 4 p.m. on Tuesday, November 10, for retaining wall work. Remembrance Day closures on November 11 and the November 8 garrison parade closure on King Street are covered in HamiltonIQ's Remembrance Day story.
Buses and Metrolinx notices
As of November 5, HSR's schedules and detours page did not list a detour for the Queenston Road lane occupancy. Metrolinx's Hamilton LRT community notices page had no construction notice newer than its utility inspection notice, which gives an estimated start date of August 31, 2026, and the City's list does not say whether the Queenston Road work is part of that inspection.
Sources
City of Hamilton
Scheduled Lane Restrictions & Road ClosuresCity of Hamilton
HSR Schedules & DetoursCity of Hamilton
Light Rail Transit (LRT)Metrolinx
Hamilton LRT - Community notices