Mountain Drive Park on Concession Street: soil removal on the east side set for December so that section can reopen, west side to follow in 2027
The City of Hamilton's project page says crews will remove soils from the east side of the closed Mountain Drive Park in December 2026 to let that section reopen, with construction on the west side starting in 2027.
The update
- Mountain Drive Park, 935 Concession Street, has had no public access since 2024 after soil tests found some soils exceed provincial standards for parkland, the City says.
- The City's timeline lists construction on the east side in December 2026 to remove site soils so the east section can reopen, and construction on the west side starting in 2027.
- The next phase includes a new spray pad, sun shelter, walkways and a replacement playground; the page gives no reopening date.
Why it matters. Residents of Raleigh and Sunninghill have been without the park since 2024, and December's work is the step the City says will let part of it reopen.
What happens in December
The City of Hamilton plans construction on the east side of Mountain Drive Park in December 2026 to remove site soils, so that the east section of the park can be reopened, according to the project timeline on the City's Mountain Drive Park page, last updated November 20, 2026. The timeline then lists 2027 for the start of construction on the west side of the site. The page does not give construction dates within December, a reopening date for either section, or a project budget.
The park, at 935 Concession Street, sits within the Ward 6 and Ward 7 boundaries and the Raleigh and Sunninghill neighbourhoods, at the eastern end of the Concession Street BIA, the City says. The Mountain Brow trail runs along its northern edge and connects it to the trail network along the top of the escarpment.
Why the park is closed
A notice at the top of the City's page reads no access to the park from 2024 to 2026. The City says standard due diligence soil testing for the park's renewal found that some of its soils exceed the Ministry of Environment, Conservation and Parks soil standards for parkland, and that out of an abundance of caution the park will remain closed until construction of the new amenities is complete. It suggests nearby parks with playgrounds, including Peace Memorial Park, Eastmount Park and Highview Park, in the meantime.
Done: March 2022
Master plan report shared with the public
Done: March to December 2023
New washroom building constructed
Done: April 2024 to February 2025
Soils exceeding provincial standards delineated
Done: March to July 2025
Detailed design revised to account for the soil findings
Next: December 2026
East side construction to remove site soils, so the east section can reopen
Next: 2027
Construction begins on the west side
What the renewal includes
The City describes the renewal as a multi-year project, informed by public engagement and a master plan prepared in 2022, because many of the park's amenities have reached the end of their lifespan. It says the next phase includes a new spray pad, a sun shelter, walkways and a replacement playground. The page puts the park's usable green space at about 7.8 acres (3.2 hectares). An older line on the same page still says construction of the new playground and spray pad was planned for 2024; the timeline on the page now runs into 2027.
The dates
Dates as this story states them, each traced to its sources.
Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.