Future schools in Hamilton
The new schools, additions and replacements the Hamilton-Wentworth District School Board and the Hamilton-Wentworth Catholic District School Board are building, have funding for or plan in Hamilton, and the sites set aside for them, each as the board's own page or plan states it.
School boards’ construction pages and accommodation plans; Ontario capital announcements · read November 27, 2026
Where the mapped future schools are in Hamilton
- Under construction
- Funded
- Board priority, unfunded
- Existing schools
4 planned schools have no position from a source this site may use, and are listed below without a map point.
Under construction
- Under construction
New Binbrook Elementary School (Ministry: Binbrook II Public Elementary School)
Binbrook, southwest corner of the community · 80 Alway Drive, Hamilton ON
K-8 school with 615 pupil places, the second HWDSB elementary school in Binbrook. A before- and after-school program is planned; no licensed child care is listed in the Ministry child-care table. Its boundary comes from the Binbrook II Boundary Review.
- Opening
- 2027-2028
- Pupil places
- 615
- Funding announced
- 2020
Funding: $29 million approved (HWDSB); Ministry Capital Priorities allocation $26,693,079 (project 21-107)
Students held at: Shannen Koostachin (new students from south Binbrook redirected since 2019)
The board’s status: under construction. HWDSB — School Construction · Not mapped: no official source this site may use gives its position.
- Under construction
New Waterdown Elementary School (Ministry: Waterdown Bay Elementary School)
Mountainview Heights neighbourhood, Skinner Road and Great Falls Boulevard, Waterdown · 34 Skinner Road, Waterdown
K-8 school with 504 pupil places and an 88-space, five-room child care centre (1 infant, 2 toddler, 2 preschool). Construction expected to start winter/early 2026 and finish summer 2027.
- Opening
- 2027-2028 (anticipated opening September 2027)
- Pupil places
- 504
- Child-care spaces
- 88
- Funding announced
- April 2024
Funding: $24.5 million provincial (HWDSB); Ministry allocations $18,360,811 Capital Priorities + $3,741,471 child care (project 21-119)
Students held at: Mary Hopkins (new JK-4 registrations in the new boundary for 2026-27)
The board’s status: under construction. HWDSB — School Construction; 2026 Capital Priorities experience · Mapped at the stated address, from the municipality's address points.
- Under construction
Mount Hope Elementary School addition
At Mount Hope Public School · Mount Hope Elementary School, Mount Hope
Permanent addition with 165 pupil places (the 2026 LTFP says 6 classrooms and 178 pupil places) and an 88-space, five-room child care centre.
- Opening
- spring 2027
- Pupil places
- 165
- Child-care spaces
- 88
- Funding announced
- 2024
Funding: $13 million approved (HWDSB 2026 Capital Priorities page); Ministry allocations $5,494,672 Capital Priorities + $4,856,892 child care (project 21-120)
The board’s status: under construction. HWDSB — 2026 Capital Priorities (ArcGIS Experience) · Mapped at the existing school's Ministry position.
Funded
- Funded
Binbrook Catholic Secondary School
Binbrook (site 'to be acquired' as of Jan 2025)
New Catholic secondary school with 1,001 pupil places. HWCDSB's 2026-27 budget release (2026-06-24) lists 'continued construction' of the school. No address, site or opening year has been published, and no attendance-area review is posted yet.
- Pupil places
- 1,001
- Funding announced
- January 28, 2025
Funding: $52 million (Ontario); Ministry Capital Priorities allocation $52,241,451 (project 47-074)
The board’s status: funded. HWCDSB — 2024-2025 Capital Priorities Announcement (Jan 28, 2025) · Not mapped: no official source this site may use gives its position.
- Funded
New Nash / Upper Stoney Creek Elementary School (Ministry: Nash Upper Stoney Creek Public Elementary School)
Upper Stoney Creek (Nash neighbourhood); new site being sourced to serve the same area
Replacement for Tapleytown, which is rated for 291 students. The school will have 650 pupil places and three child care rooms. In September 2025 HWDSB dropped the 399 First Road West site on Ministry direction and is looking for a new property. No opening date has been set.
- Pupil places
- 650
- Child-care spaces
- 49
- Funding announced
- December 6, 2021
Funding: $16.7 million announced (HWDSB); Ministry allocations $14,933,170 Capital Priorities + $1,734,751 child care (project 21-115)
The board’s status: funded. HWDSB — Update on New Nash Elementary School (Sept 30, 2025) · Not mapped: no official source this site may use gives its position.
- Funded
St. Paul Catholic Elementary School addition
At St. Paul Catholic Elementary School
Addition with 141 pupil places and a three-room, 49-space child care centre. The 2026-27 budget describes it as a five-classroom addition and child care centre. No opening date published.
- Pupil places
- 141
- Child-care spaces
- 49
- Funding announced
- January 28, 2025
Funding: $6.9 million (Ontario); Ministry allocations $4,595,805 Capital Priorities + $2,276,550 child care (project 47-075)
The board’s status: funded. Ontario Investing $67 Million to Construct and Expand Three Hamilton-Area Schools (Jan 28, 2025) · Mapped at the existing school's Ministry position.
- Funded
Janet Lee Elementary School addition
At Janet Lee Public School · Janet Lee Elementary School, Stoney Creek
Addition with 162 pupil places and 88 licensed child care spaces; in design per HWDSB (Nov 2026).
- Opening
- spring 2028
- Pupil places
- 162
- Child-care spaces
- 88
- Funding announced
- January 28, 2025
Funding: $7.8 million (Ontario, Jan 28, 2025); Ministry allocations $4,000,234 Capital Priorities + $3,753,900 child care (project 21-123)
The board’s status: funded. HWDSB — 2026 Capital Priorities (ArcGIS Experience); Ontario release Jan 28, 2025 · Mapped at the existing school's Ministry position.
- Funded
Lake Avenue Elementary School addition
At Lake Avenue Public School · Lake Avenue Elementary School, Hamilton (Lower Stoney Creek)
Addition with 176 pupil places, a new gym and interior renovation, in design. The June 2026 LTFP said there was no Ministry response yet. The Ministry list dated 2026-06-30 and HWDSB's November 2026 page both show it funded. Exact announcement date not found.
- Opening
- spring 2029
- Pupil places
- 176
Funding: $13 million approved (HWDSB); Ministry Capital Priorities allocation $13,591,050 (project 21-124-C01)
The board’s status: funded. Ontario Ministry of Education — List of Schools Eligible for Funding (June 30, 2026) · Mapped at the existing school's Ministry position.
Board priority, unfunded
- Board priority, unfunded
New elementary school, Fruitland-Winona secondary plan area
Fruitland-Winona secondary plan area, Stoney Creek
The 2026 LTFP calls for land acquisition for a new elementary school in the short term. Winona Elementary is projected at 154% utilization by 2035. No funding or site has been announced.
The board’s status: capital priority (unfunded). HWDSB 2026 Long-Term Facilities Plan (Planning Area 08: Lower Stoney Creek) · Not mapped: no official source this site may use gives its position.
- Board priority, unfunded
Rousseau reconstruction (to close Frank Panabaker North)
At Rousseau Public School · Ancaster
The Ministry has not funded a rebuild of Rousseau, which is needed to complete the 2017 Accommodation Review and close Frank Panabaker North. The 2026 LTFP plans another capital priorities submission in the short term.
The board’s status: capital priority (unfunded). HWDSB 2026 Long-Term Facilities Plan (Planning Area 10: Ancaster) · Mapped at the existing school's Ministry position.
School boundary reviews in HamiltonAll Hamilton schoolsHWDSB: School construction
Reviews and future schools as each school board's own pages, plans and reports state them, with the page that says so. Boards change plans, dates and boundaries; the board's page is the authority. A planned school’s attendance area is set by the board in a boundary review, usually shortly before it opens. Boundary reviews and future schools as each school board's own pages, plans and reports state them, read by a person and recorded with the page that says so. A school a review names is matched to the Ministry list by name within its board. A future school is mapped only where an official source this edition may use places it: the Ministry's coordinates for a project at an existing school, or the board's stated civic address matched to the municipality's address points. Attendance-area boundaries are not reproduced: no board serving this edition licenses them for reuse (see boards[].boundaryData).
Sources
Every factual claim above traces to one of these documents.
Hamilton-Wentworth District School Board
HWDSB — 2026 Capital Priorities (ArcGIS Experience)Retrieved November 27, 2026
Hamilton-Wentworth Catholic District School Board
HWCDSB — 2024-2025 Capital Priorities Announcement (Jan 28, 2025)Retrieved November 27, 2026
Hamilton-Wentworth District School Board
HWDSB — Update on New Nash Elementary School (Sept 30, 2025)Retrieved November 27, 2026
Hamilton-Wentworth Catholic District School Board
Ontario Investing $67 Million to Construct and Expand Three Hamilton-Area Schools (Jan 28, 2025)Retrieved November 27, 2026
Government of Ontario
Ontario Ministry of Education — List of Schools Eligible for Funding (June 30, 2026)Retrieved November 27, 2026
Hamilton-Wentworth District School Board
HWDSB 2026 Long-Term Facilities Plan (Planning Area 08: Lower Stoney Creek)Retrieved November 27, 2026