New schools and additions planned in Hamilton: what is funded, what is being built and what is paused

Hamilton's public board is building new elementary schools in Binbrook and Waterdown and has three additions funded; a Stoney Creek school is paused. The Catholic board has a Binbrook high school and two additions funded. Here is each, as of November 18, 2026.

HamiltonIQ Newsroom7 sources · 6 min read

Email

The details

What is funded, under construction or paused

A school board cannot build a new school or a large addition until the Ministry of Education approves the money, usually through its Capital Priorities Program. The table lists the Hamilton projects that have that approval at the Hamilton-Wentworth District School Board (HWDSB) and the Hamilton-Wentworth Catholic District School Board (HWCDSB), along with a French-language secondary school for which the City has agreed to provide land. Each row gives the stage and dates the board, the Province or the City has published, as of November 18, 2026.

New schools and major additions in Hamilton, from the school boards', Ontario's and the City's published documents, as of November 18, 2026
New Binbrook Elementary School (HWDSB)
Under construction at 80 Alway Drive, as a second elementary school for the Binbrook community, with 615 elementary student spaces and $29 million in approved funding. The board's September 29, 2026 capital update lists it at the construction phase with construction ongoing. The board's boundary review page gives the 2027-2028 school year for its opening.
New Waterdown Elementary School (HWDSB)
Under construction in the Mountainview Heights neighbourhood, at Skinner Road and Great Falls Boulevard. The board's project page describes 504 new student spaces for Kindergarten to Grade 8, an 88-space child care centre and $24.5 million in provincial funding, with construction completion anticipated in summer 2027 and the school opening in September 2027.
New Upper Stoney Creek (Nash) Elementary School (HWDSB)
Paused. A 650-pupil-place replacement for Tapleytown Elementary School with three child care rooms, for which $16.7 million in funding was announced. On September 30, 2025 the board said that, on Ministry of Education direction, it will not build at 399 First Road West and is looking for a new property serving the same area. Its September 29, 2026 capital update lists the project as paused.
Mount Hope Elementary School addition (HWDSB)
Under construction. A 165-pupil-place addition with 88 licensed child care spaces. The board's September 29, 2026 capital update describes a six-room addition with a Kindergarten renovation and a five-room child care centre, a multi-year budget of about $13.2 million and construction ongoing.
Janet Lee Elementary School addition (HWDSB)
In design. A 162-pupil-place addition with 88 licensed child care spaces. The board's September 29, 2026 capital update describes a six-room addition with a learning commons and main office renovation and a five-room child care centre, and a multi-year budget of about $7.8 million. It records Ministry approval in spring 2025 and a site plan approval submission completed on March 2, 2026.
Lake Avenue Elementary School addition (HWDSB)
In design. A 176-pupil-place addition including a new gym and interior alterations to the existing school. Ontario listed it among its approved school projects on June 29, 2026, at $13.6 million. The board's September 29, 2026 capital update records Ministry approval in spring 2026 and anticipates a site plan approval submission in spring 2027.
Binbrook Catholic Secondary School (HWCDSB)
Funded. On January 28, 2025 the board announced provincial capital funding for a new Binbrook Catholic Secondary School with 1,001 pupil places, part of $59,113,806 awarded together with an addition at St. Paul Catholic Elementary School. The announcement gives no site address, construction start or opening date.
St. Paul Catholic Elementary School addition (HWCDSB)
Funded. A 141-pupil-place addition with a three-room child care centre, announced by the board on January 28, 2025 together with the Binbrook secondary school. The announcement gives no construction start or opening date.
Our Lady of the Assumption Catholic Elementary School addition (HWCDSB)
Funded. Ontario's June 29, 2026 list of approved school projects includes a 164-student-space addition with 49 licensed child care spaces at the school, at $9.1 million. The list gives no construction or opening date.
Joint French-language secondary school, 700 Garner Road East
Land agreed. On February 25, 2026 the City of Hamilton, Conseil scolaire catholique MonAvenir and Conseil scolaire Viamonde signed a land exchange agreement that secures 700 Garner Road East, a 14-acre City-owned site in Ward 12, for a joint secondary school. The City says the boards plan a facility for about 400 students per board in separate wings. Its release gives no opening date.

The public board's three new schools

HWDSB's School Construction page describes the new Binbrook school as moving forward and in construction, and the board's boundary review for it was approved in March 2026. For Waterdown, the page gives an anticipated construction start of winter or early 2026 and says the project is under construction; the child care centre is to have two preschool rooms, two toddler rooms and an infant room.

One figure differs between the board's documents. The project page gives the new Waterdown school 504 student spaces, while the September 29, 2026 capital update describes it as a 650-pupil-place Kindergarten to Grade 8 school with a five-room child care centre. Both documents give funding of about $24.5 million.

The Upper Stoney Creek school has had the longest road. The board bought land in November 2020 and received Ministry approval in December 2021. Trustees paused the build in December 2023 to look into conditions related to the nearby GFL Stoney Creek Regional Facility, and in October 2024 approved going ahead at the original site. The board says it was told in mid-August 2025 that a change of location was required. It has not published a new site or timeline, and says the school will still serve Tapleytown Elementary School families, whose current school opened in 1881 and is rated for 291 students.

Three additions at public schools

The capital update lists six projects under Capital Priorities, each with a multi-year budget: the three new schools and additions at Mount Hope, Janet Lee and Lake Avenue. For Janet Lee it says the Ministry's approval to proceed was to be issued in September 2026. For Lake Avenue it describes a new gym and four-room addition with a four-room interior renovation, a learning commons and a main office renovation.

The Catholic board's projects

HWCDSB's January 28, 2025 announcement quotes its chair thanking the Province for capital funding for the Binbrook secondary school and the St. Paul addition, and thanking MPP Donna Skelly for her advocacy. HamiltonIQ did not find a later page on the board's site giving a location, a construction schedule or an opening date for either.

Separately, the City of Hamilton gave notice on January 23, 2026 of a rezoning application by the board for 2655 Fletcher Road in Glanbrook, in Ward 11, for a two-storey secondary school with parking and drop-off areas, an all-season sports field and a running track. The board's funding announcement does not name a site and the City's notice does not name the school, so this page does not treat them as one project. HamiltonIQ's earlier story covers the rezoning.

The French-language secondary school

The City's release on the land exchange says the agreement also brings 16 Broughton Avenue, a 9.5-acre site in Ward 6, into public ownership as parkland, and that Council ratified moving forward with the exchange on July 8, 2022. The planned school's shared spaces may include an auditorium, a cafeteria and vocational classrooms. The City says it is still working with the boards and the owner of the surrounding subdivision to complete the exchange.

How a project moves, and where to follow it

  • HWDSB lists the steps for a new school as buying property where needed, Ministry funding, design and budget, Ministry approval to proceed, site plan approval from the City, tendering for a general contractor and construction.
  • HWDSB's School Construction page has a section for each new school and addition, and links the board's latest quarterly capital update.
  • HWDSB's Boundary Reviews page carries the reviews tied to the Binbrook and Waterdown schools.
  • Ontario announces funding approvals on its news site; HWCDSB posts its announcements on its own news pages.

Sources

Every factual claim above traces to one of these documents.

  1. Hamilton-Wentworth District School Board

    School Construction

    Retrieved November 18, 2026

  2. Hamilton-Wentworth District School Board

    Quarterly Capital Update, Executive Report to Finance & Facilities Committee, September 29, 2026

    Published September 29, 2026 · Retrieved November 18, 2026

  3. Hamilton-Wentworth District School Board

    Boundary Reviews

    Retrieved November 18, 2026

  4. Hamilton-Wentworth Catholic District School Board

    2024-2025 Capital Priorities Announcement

    Published January 28, 2025 · Retrieved November 18, 2026

  5. Province of Ontario

    Supporting School Infrastructure Projects in Ontario

    Published June 29, 2026 · Retrieved November 18, 2026

  6. City of Hamilton

    City and French public and Catholic school boards sign land exchange

    Published February 25, 2026 · Retrieved November 18, 2026

  7. City of Hamilton

    Public Meeting for 2655 Fletcher Road, Glanbrook

    Published January 23, 2026 · Retrieved November 18, 2026