Ontario approved $22.7 million in June 2026 for school additions at Lake Avenue Elementary and Our Lady of the Assumption in Hamilton

A provincial list published on June 29, 2026 included two Hamilton projects: a 176-student-space addition to Lake Avenue Elementary School and a 164-student-space addition with 49 child care spaces at Our Lady of the Assumption Catholic Elementary School.

HamiltonIQ Newsroom2 sources · 2 min read

Email

The details

What was announced

On June 29, 2026, the Province of Ontario published the list of school construction projects it had approved through its capital priorities program. The list covered 79 projects across the province worth $1.6 billion, including $87 million in child care capital funding, and was expected to create more than 29,000 student spaces and over 1,900 licensed child care spaces. Two of the projects are in Hamilton, one for each of the city's English-language boards.

The two Hamilton projects on the provincial list
Lake Avenue Elementary School (HWDSB)
176-student-space addition, $13.6 million
Our Lady of the Assumption Catholic Elementary School (HWCDSB)
164-student-space addition and 49 licensed child care spaces, $9.1 million
Combined provincial funding
$22.7 million
Combined new student spaces
340

The two schools

Lake Avenue is a junior kindergarten to Grade 8 public school at 157 Lake Avenue North in Stoney Creek. The Ministry of Education's school dataset, which lists it under the name Lake Avenue Public School, records an enrolment of 730. The province's addition adds 176 spaces to the existing building. The project does not include child care spaces.

Our Lady of the Assumption is a junior kindergarten to Grade 8 Catholic school at 103 Fletcher Road, in the growing area on the upper Stoney Creek and Glanbrook side of the city, with an enrolment of 790 in the same dataset. Its addition pairs 164 student spaces with 49 licensed child care spaces, which is the same child care count the province attached to several other elementary additions on the list.

How the funding works

The province said 67 of the 79 projects were approved for $1.3 billion through the 2025-26 capital priorities round and the remaining 12 shared nearly $300 million through the 2026-27 round. The list does not say which round each Hamilton project came from. The province described the program as addressing local student space pressures. The funding figure is the province's share as listed; the backgrounder does not give a design, tender or construction timetable for any project.

Where it stands now

The funding was approved in June 2026. When HamiltonIQ checked on November 10, 2026, neither the Lake Avenue school website nor the boards' public sites carried a construction schedule, design or opening date for either addition, so no start or completion date can be given. Families at either school should expect the board to announce timing and any disruption during construction directly.

Sources

Every factual claim above traces to one of these documents.

  1. Province of Ontario

    Supporting School Infrastructure Projects in Ontario

    Published June 29, 2026 · Retrieved November 10, 2026

  2. Hamilton-Wentworth District School Board

    Lake Avenue Elementary School

    Retrieved November 10, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.


Go deeper

All stories