Main Street's two-way conversion from Dundurn to the Delta has a $26.2-million budget, with construction planned from late 2026 through 2027
Hamilton told Council in June 2026 that the Main Street renewal, which converts the street to two-way traffic from Dundurn Street to the Delta and adds bike lanes from Victoria to Sherman, was headed to tender with a $26.2-million budget.
The details
What the City reported
In a communication update to Council dated June 5, 2026, Hamilton's Engineering Services director set out the status of the Main Street Renewal and Redesign Project, which carries out Council's May 2022 direction to convert Main Street from one-way to two-way traffic as part of safety improvements on downtown arterial roads. Detailed design was complete and the project was moving to a two-stage tender, starting with pre-qualification of bidders. Staff expected the formal tender to begin in early July for a September 2026 construction start, with all work finished by the end of 2027.
- Full road resurfacing from Dundurn Street to King Street East at the Delta.
- Rebuilding all curb ramps at intersections to Accessibility for Ontarians with Disabilities Act standards.
- Curb extensions and greening east of Sherman Avenue and at other locations.
- Enhanced cycling facilities between Victoria Avenue and Sherman Avenue.
- New traffic signals and street lighting, and conversion of the roadway to two-way traffic.
How each section will look
From Dundurn Street to Victoria Avenue, staff said, the street will generally have three eastbound lanes and one westbound lane as far as Bay Street, then two through lanes eastbound with one westbound lane and turn lanes to Victoria. The design removes the slip-off right turn from Main onto Dundurn Street South, adds buffers along both curbs and places median islands at Catherine, Ferguson and Wellington streets, with new signals and crossings at Strathcona Avenue and Ferguson Avenue, according to the project page. Staff said this section offers similar capacity to the three-lane layout in place since 2022.
From Victoria Avenue to Sherman Avenue, Main Street will have two eastbound lanes, one westbound lane and turn lanes, with cycle lanes in each direction separated by curbs and flex posts and protected-intersection designs at Victoria and Sherman. Staff said the bike lanes do not reduce the number of traffic lanes. From Sherman Avenue to the Delta, the north curb lane, now closed to through traffic by temporary concrete barriers, becomes permanent on-street parking with curb extensions and tree planting, and the rail crossing at Gage Avenue is improved.
- About $10 million
- $3.4 million
- $8.4 million
- $4.4 million
- $26.2 million, approved in the 2025 budget and affirmed in 2026
Where it stands now
The City's project StoryMap at hamilton.ca/mainstreetcorridor, last updated October 2, 2026 when HamiltonIQ checked it on November 11, says construction is planned to begin in late 2026 and continue through 2027, coordinated with other infrastructure work in the lower city. That is later than the September start the June update anticipated. The page notes that watermain lining between Dundurn Street and Victoria Avenue, which began in late March, is under way ahead of the redesign and may bring lane restrictions and night work. HamiltonIQ found no published contract award or construction start date as of November 11.