Hamilton proposes a 3% increase to building permit fees, with a public meeting at Planning Committee on December 1
The Planning Committee will hold a public meeting on December 1, 2026 at 9:30 a.m. on a draft by-law that would raise existing building permit fees by 3%. Written comments and requests to speak are due by noon on November 30.
The details
What is proposed
The City of Hamilton's Planning Committee will consider a report at a public meeting, including a draft by-law, that proposes an increase of 3% to existing building permit fees, according to a public notice issued on November 10, 2026. The notice says the increase is to cover reasonable expected costs for activities performed under the Building Code Act, 1992.
Nothing has been decided. The notice says that, subject to the holding of the public meeting, the recommendations of the Planning Committee and the decision of City Council, it is staff's proposal to enact a by-law under section 7 of the Building Code Act, 1992, imposing the proposed fees by amending Building By-law No. 15-058. The notice does not list the proposed fees in dollars or say when they would take effect. It says information on the estimated costs of administering and enforcing the Act, and on the rationale for increasing the fees, is available without cost on request.
The meeting
- December 1, 2026 at 9:30 a.m.
- Hamilton City Hall, Council Chambers, 2nd Floor, 71 Main Street West, Hamilton
- Hybrid: in person and on the Webex platform
- Must be received by 12 noon, Monday, November 30, 2026
- Delegation request forms must be received by 12 noon, Monday, November 30, 2026
- Requests must be received by 12 noon, Friday, November 27, 2026
The notice says the fee proposal will be one of a number of items reviewed at the Planning Committee meeting. Members of the public can also view the meeting online or on the City's YouTube channel.
How to comment
- In writing: by email, or by mail to the Legislative Coordinator of the committee, City of Hamilton, 71 Main Street West, 1st Floor, Hamilton, Ontario, L8P 4Y5. Comments must be received by 12 noon on Monday, November 30, 2026.
- By speaking: virtually, through Webex by computer or phone, or in person. People wishing to delegate are encouraged to pre-register through the City's Request to Speak to a Committee of Council page, and delegation request forms must be received by the Office of the City Clerk no later than 12 noon on Monday, November 30, 2026.
- By pre-recorded video: submitted with a request to speak form, and received by the Office of the City Clerk no later than 12 noon on Friday, November 27, 2026.
Any written comments received after the deadline will be included on the Wednesday, December 9, 2026 Council agenda, the notice says. The email address for written comments is on the City's notice.
What the fees are now
Permit fees must be paid when a building permit application is submitted and are determined by Hamilton's Building Permit By-law 15-058, the City's Building Permit Fees page says. Under the schedule printed there, the fee is the service index for the class of work multiplied by the floor area of the work in square metres, unless the schedule says otherwise. Where no new floor area is created, the fee is 1% of the prescribed value as determined by the Chief Building Official, subject to a minimum fee. Fees are rounded off to the nearest full dollar.
- $291
- $18.32 per square metre
- $18.32 per square metre
- $515 flat fee
- $1,030 flat fee
- $5.36 per square metre
- $6.58 per square metre
- $4.06 per square metre