Widening Rymal Road between Upper James and Dartnall is estimated at $107 million, with construction planned from 2028 to 2031

City staff told Council in July 2026 that the five-kilometre Rymal Road widening between Upper James Street and Dartnall Road, cleared of its last environmental assessment hurdle, will cost about $107 million and be built in phases from 2028 to 2031.

HamiltonIQ Newsroom1 source · 2 min read

Email

The details

What staff told Council

In a communication update to Council dated July 28, 2026, Hamilton's Engineering Services division set out the plan for improving Rymal Road between Upper James Street and Dartnall Road, an approximately five-kilometre stretch across Wards 6, 7 and 8. Staff called it one of the largest construction projects the City will undertake over the next few years.

The environmental assessment for the corridor calls for widening the road by one lane in each direction, adding and improving facilities for walking and cycling, and upgrading stormwater management. Staff said the work will also support Rymal Road's role as a major transit corridor on the HSR's planned rapid network, as the S-Line, and as a designated truck route. With the assessment filed, the project is now in detailed design. Staff said all outstanding approvals tied to the assessment have been resolved, including a Section 16 Order request, a public request for the Ministry of the Environment, Conservation and Parks to review the widening.

Rymal Road, Upper James Street to Dartnall Road, from the July 28, 2026 update
Length
About 5 kilometres
Work
One added lane each way, active transportation, stormwater upgrades
Cost estimate
About $107 million ($88 million road and storm sewers; $19 million other subsurface infrastructure)
Detailed design and tender
Over the next two years
Construction
Planned 2028 to 2031, phased over about four years
Wards
6, 7 and 8

Timing and coordination

Staff said a terms of reference for a detailed design consultant was being prepared and that early work, such as Stage 2 archaeological assessments and geotechnical studies, was being advanced to speed up the tender. Construction would be phased over about four years because of the project's size and the need to coordinate with other major work, including the Stone Church Feeder Main watermain project. Staff said they are examining alternatives to accelerate the 2028 to 2031 timeline.

Before reconstruction, staff said, the City may carry out minor resurfacing and patching over the next year or two, limited to keep throw-away costs down, and will continue maintaining the road to the Minimum Maintenance Standards.

Funding and where it stands now

Staff described the widening as critical to residential and employment growth, calling Rymal Road the major east-west corridor on the Mountain and a key link between the Airport Employment Growth District and the Red Hill Business Park. Staff noted that the City had applied to the federal-provincial Development Charges Reduction Program, as set out in a report to the June 17 General Issues Committee, with Rymal Road and Garner Road among five projects submitted. On August 26, 2026, Ontario and Canada announced $572 million for Hamilton through that program, and the projects named included widening Rymal Road between Upper James Street and Dartnall Road, with construction to begin in 2028. As of November 11, 2026, HamiltonIQ found no later public notice of a design consultant award or a revised schedule.

Sources

Every factual claim above traces to one of these documents.

  1. City of Hamilton

    Communication Update: Advancing Rymal Road Improvements (ENG2604)

    Published July 28, 2026 · Retrieved November 11, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.