Birch Transit Centre, HSR's $390.4 million second bus garage, opened in June 2026 with indoor storage for 200 buses
The City announced the opening of the Birch Transit Centre on June 23, 2026. The $390.4 million maintenance and storage facility, funded by all three levels of government, gives Hamilton Street Railway a second garage after its existing one reached capacity.
The details
What opened
On June 23, 2026, the City of Hamilton announced the opening of the Birch Transit Centre, a new maintenance and storage facility for Hamilton Street Railway buses. The City put the project cost at $390.4 million. Construction began in 2023 and, according to the City, is complete.
The facility gives HSR a second garage. The City's release says that as HSR added buses to meet demand, its existing maintenance and storage facility reached capacity; with Birch open, the fleet is supported from two locations. The City's page for the facility says it has storage for 200 buses, with the capacity to add a further 100 spaces, and the caption on a City construction video places it at 281 Birch.
- $390.4 million
- $142.8 million
- $92.6 million
- $155 million
- Began 2023; completed 2026
- 200 buses indoors, with capacity for 100 more
- Bus washing systems, administrative space, infrastructure for future battery-electric buses
Why a second garage matters
A bus system can only run as many buses as it can park, fuel, wash and repair overnight. The City describes the centre as a key component of HSR Next, its multi-year plan to expand and redesign the transit network, and says the building will help keep buses maintained, protected from the weather and available for service. The release also says the centre is built with the infrastructure to support battery-electric buses in future; it does not say when electric buses will be bought or how many.
The release does not say how many buses moved to Birch on opening, how many staff work there, or whether the final cost matched the approved budget.
Where it stands now
The City's Birch Transit Centre web page, read on November 9, 2026, describes the facility as completed in 2026 and in use for storing and maintaining buses. The service changes the added capacity is meant to support are still ahead: HSR's proposed fall 2027 network changes went to public consultation in 2026, and a report titled HSR 2027 Annual Service Plan was on the General Issues Committee agenda on September 28, 2026.
Sources
City of Hamilton
Birch Transit Centre