Skip to content

Analysis

Hamilton housing supply

How much housing is planned, where, and how far along: the residential projects on the planning record, in aggregate, beside the homes being started.

Provincial ten-year target
47,000
New homes
Homes started
1,939
CMHC, Sep 2025 to Aug 2026
Residential projects on the record
122
The City of Hamilton’s planning record
Filed in the last 5 years
77
No status published

Read October 9, 2026. Sources below.

The answer

The City of Hamilton’s planning record holds 122 projects that would add homes in Hamilton: plans of subdivision and plans of condominium. 77 of them were filed in the last 5 years; the record publishes no status, so none is described as approved or built. Over Sep 2025 to Aug 2026, CMHC counted 1,939 housing starts.


What is being built, against the target

The provincial target

The Province set Hamilton a target of 47,000 new homes over ten years. It has counted 10,196 since 2022, 22% of the ten-year figure. For 2024 the target was 3,917 and the Province counted 2,384, recording the year as “not met”.

The Province's count of housing progress, which it says may differ from CMHC housing starts. Source: Province of Ontario, Ontario’s housing supply progress (2024 file), Open Government Licence – Ontario.

Housing starts by kind of home

Housing starts in Hamilton by dwelling type, Sep 2025 to Aug 2026
Dwelling typeStartsShare
Single-detached1809%
Semi-detached121%
Row874%
Apartment1,66086%
All1,939

The totals are our sums of CMHC’s monthly figures; a start is counted when the foundation is complete. Source: Canada Mortgage and Housing Corporation (CMHC), Starts and Completions Survey (Housing Market Information Portal, Table 1.2.1), Sep 2025 to Aug 2026.

Month-by-month starts, rents and vacancy are on Hamilton housing. A start is a home under construction; an application below is a proposal that may never reach one.


Residential projects by filing year

City of Hamilton publishes the year each application was filed but no status, so the record is counted by when it was filed. A project filed over several years sits in its latest.

FiledResidential projects
20267
20259
202411
202315
202218
202117
202011
20198
201811
20176
20169

By ward

WardResidential projectsFiled in the last 5 years
Ward 111
Ward 233
Ward 311
Ward 42—
Ward 543
Ward 686
Ward 742
Ward 854
Ward 91911
Ward 101811
Ward 111711
Ward 122110
Ward 1388
Ward 142—
Ward 1596

By community

CommunityResidential projectsFiled in the last 5 years
Stoney Creek3420
Hamilton3020
Ancaster2110
Glanbrook2013
Flamborough1310
Dundas44

How to read this

A project counts as residential when it is a plan of subdivision or a plan of condominium. Counts are of projects, not applications: one redevelopment usually files several applications describing the same homes, and each project is counted once. City of Hamilton publishes no unit counts with its applications, so this page counts projects and never homes; a rezoning for an apartment tower that is neither a subdivision nor a condominium file is not identifiable as residential from the record and is left out.

Three different things are measured here and they do not add together. The target is the Province’s count of homes it wants built. A start is a home CMHC has counted under construction. A planning application is permission being sought or granted; an approval is not a building, and a project can be revised, refused, appealed or left unbuilt.

Sources

Every factual claim above traces to one of these documents.

  1. City of Hamilton

    Development Applications (Open Hamilton)

    Retrieved October 8, 2026

  2. Canada Mortgage and Housing Corporation (CMHC)

    Housing Market Information Portal, Table 1.2.1: Housing starts by dwelling type, monthly

    Retrieved October 9, 2026