Hamilton's ASI Marine wins a $9.2-million contract on Ontario's first small modular reactor at Darlington

Hamilton-based ASI Marine will help with tunnel-boring machine operations at Ontario Power Generation's Darlington New Nuclear Project under a $9.2-million contract, one of 14 the Province announced for Greater Toronto and Hamilton Area companies.

HamiltonIQ Newsroom2 sources · 2 min read

Email

The details

The Hamilton contract

ASI Marine, a Hamilton-based company, has been awarded a $9.2-million contract to assist with tunnel-boring machine operations at Ontario Power Generation's Darlington New Nuclear Project, where the first of four planned small modular reactors is being built. The Ministry of Energy and Mines announced the contract on November 6, 2026, among awards to manufacturers and suppliers in the Greater Toronto and Hamilton Area.

The Province says the Hamilton contract supports good-paying jobs in the region. It does not say how many people will work on it in Hamilton, or when the work starts.

ASI Marine is proud to have our Stoney Creek team supporting construction of the G7's first small modular reactors at Darlington.
David Ritchie, President, ASI Marine, in the Province's release

In the same statement, Ritchie said the company is contributing its own inspection technology and a specialized Ontario workforce. The release does not describe the tunnel-boring work in more detail.

The wider announcement

According to the release, 14 contracts went to Greater Toronto and Hamilton Area companies supplying components and services such as transformers, pumps, specialized steel and concrete, and together they will add more than $110 million to Ontario's GDP. The accompanying backgrounder names 12 recipient companies; ASI Marine is the only one listed as based in Hamilton. Nearby recipients include two Oakville firms, Promation and Hooper Welding, and Burlington's Clyde Union Canada.

One of those has a Hamilton connection of its own. Hooper Welding, which the Province lists as based in Oakville and which has a $1.7-million contract to supply steel for the reactor's structural modules, said in the release that it is investing in a new dedicated nuclear manufacturing bay in Hamilton with 300-tonne crane capacity and direct harbour access. The statement, from vice-president Chris Hooper, gives no address or opening date for the bay.

From the Province's November 6 release and backgrounder
Hamilton recipient
ASI Marine
Contract value
$9.2 million
Work
Assisting with tunnel-boring machine operations
Project
Darlington New Nuclear Project (Ontario Power Generation), first of four planned small modular reactors
Contracts announced
14, to 12 Greater Toronto and Hamilton Area companies
Provincial estimate
More than $110 million added to Ontario's GDP

The Province frames the contracts as part of its response to U.S. tariffs, saying the reactor build is opening new markets for tariff-affected sectors such as steel and concrete, and that it has worked with Ontario Power Generation so that 80 per cent of project spending goes to Ontario companies.

Sources

Every factual claim above traces to one of these documents.

  1. Province of Ontario

    Ontario Awards Contracts to GTHA Manufacturers to Build G7's First Small Modular Reactor

    Published November 6, 2026 · Retrieved November 9, 2026

  2. Province of Ontario

    Ontario Awards Contracts to GTHA Manufacturers to Build G7's First Small Modular Reactor (backgrounder)

    Published November 6, 2026 · Retrieved November 9, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.


Go deeper

All stories